We started with concrete grade of M20 and today with Lot of R&D and innovative steps, we could achieve concrete grade of M70 for our Projects with In- House production of concrete using Site RMC plants. We documented each and every construction activity and made our own quality standards in the form of Syllabus, Handbooks etc , which then became our “Holy Book” which reflected our Commitment and Clarity for Quality , having a state of art holistic approach .
Indian standard code IS 456 got revised in year 2000 in which few new recommendations were made , whereas we started implementing all of them way back in year 1992 !!!
We have developed in house capability of carrying out Concrete Mix Design and formwork design , as per the Training given by our Guru Er Anthony P Remedios , to ensure required Quality and Speed is achieved.
We started Powai and Thane with Low rise buildings of 7 floors and now with high grade concrete we are going for tall building of 36 floors and further plan to raise building height to 50 floors in future.
During my professional carrier of 44 Years , I find that today we have achieved reasonably good quality standards. But it is said that it is easy to reach on top , but difficult to remain at top & consolidate the position achieved . Continuous Learning and Innovating with Determination, Passion and Smart work is the need of the hour. We cannot sit on our past laurels , on the assumption that now nothing is left to learn. In fact one has to keep Learning , upto the very end of ones life .
Now the construction scenario is fast changing. Expectations of customers are increasing in terms of Quality, Speed, Final product and After Sales services. One has to be on his toe and one can’t relax. What you have learnt , achieved and thought “ The Best” is now tending to become ZERO . We require to achieve in Future , Better & Better Construction Standards than the Best , achieved so far.
In today’s environment we have to also ensure required speed and meet stringent timelines for finishing Projects , while maintaining required Quality Standards within given Budget.
Today it is a challenge to balance both Quality and Speed with available resources. Our beliefs, mindset, assumption and thought process, working pattern required to be revisited and we have to have fresh thinking , for every aspect of Construction.
Our functional pattern and strategy are now updated and upgraded with modern tools and techniques.
Right from Planning stage of Projects, Construction aspects like Quality, Speed, Finance, Time Lines and Logistics are well identified.
We used to have slab cycle of 20 days. Now we have to ensure slab cycle of 9 days for same quantum of works. Thus Modernization of Construction Techniques in terms of Formwork, Concrete Mix Design, Mechanization etc need to be suitably upgraded.
As on today , we have completed , in the last 5 years , volume of Construction works ,which we had been done in last 20 years , at all our Mumbai Projects , with the Quality Standards being maintained . This itself speaks volumes , about Hiranandani Constructions , which has no competitor at all . In fact we are ourselves Our Competitor , doing always better than our Previous Best .Thus we have become a Iconic Organization , laying the foundation , of the much needed Quality Standards, in Mumbai , but also I may say Proudly even in India .